# ERP go-live — cut-over plan (Nexora ERP) **Project manager:** Samuel Nguyen · **Executive sponsor:** Marie-Ève Lacasse · **Version:** 2.1 (2025-11-05) ## Status Data migration dress rehearsal completed on November 1 with 99.6 % reconciliation of open items. Two open defects on the production scheduling module, both in the November 14 patch. Training completion: 91 % of end users. ## Cut-over timeline | Step | Date / time | Who | Notes | |---|---|---|---| | Go/no-go readiness review | 2025-11-19 10:00–11:00 | CEO, CFO, PM, IT | Boardroom B | | Patch deployment (scheduling defects) | 2025-11-14 | IT / Nexora | | | Freeze of legacy transactions | 2025-11-21 12:00 | All departments | | | **War-room kick-off — go/no-go sign-off** | **2025-11-21 14:00–15:00** | **CEO (required), CFO, PM, IT, Operations** | Boardroom A, head office; the CEO signs the cut-over authorisation in person | | Data migration and validation | 2025-11-22 06:00 → 2025-11-23 18:00 | PM, IT, Finance | | | Go-live | 2025-11-24 06:00 | All | Hypercare for 2 weeks | ## Presence requirements The cut-over authorisation must be signed by the CEO at the war-room kick-off on Friday, November 21 at 14:00; if the CEO cannot be present in person, a written delegation to the CFO must be issued beforehand. ## Risks - Scheduling defects not closed by November 14 → fallback: go-live postponed to December 1. - Key users unavailable during the cut-over weekend.