# ERP go-live — cut-over plan (Nexora ERP)

Project manager: Samuel Nguyen · Executive sponsor: Marie-Ève Lacasse · Version: 2.1 (2025-11-05)

# Status

Data migration dress rehearsal completed on November 1 with 99.6 % reconciliation of open items. Two open defects on the production scheduling module, both in the November 14 patch. Training completion: 91 % of end users.

# Cut-over timeline

Step Date / time Who Notes
Go/no-go readiness review 2025-11-19 10:00–11:00 CEO, CFO, PM, IT Boardroom B
Patch deployment (scheduling defects) 2025-11-14 IT / Nexora
Freeze of legacy transactions 2025-11-21 12:00 All departments
War-room kick-off — go/no-go sign-off 2025-11-21 14:00–15:00 CEO (required), CFO, PM, IT, Operations Boardroom A, head office; the CEO signs the cut-over authorisation in person
Data migration and validation 2025-11-22 06:00 → 2025-11-23 18:00 PM, IT, Finance
Go-live 2025-11-24 06:00 All Hypercare for 2 weeks

# Presence requirements

The cut-over authorisation must be signed by the CEO at the war-room kick-off on Friday, November 21 at 14:00; if the CEO cannot be present in person, a written delegation to the CFO must be issued beforehand.

# Risks

  • Scheduling defects not closed by November 14 → fallback: go-live postponed to December 1.
  • Key users unavailable during the cut-over weekend.